Woodside Energy LtdLow Temperature Assessment for 15 Vessels
Low Temperature assessment for 15 vessels installed on FPSO OKHA per AS1210 and ASME
Apache Energy
Design Checks of Piping and Vessel
Design checks of pipe with exceeded design pressure. Check of vessel for re-rate or replacement
Nickel West
Re-rate of Intercooler and Calculation of New Corrosion Allowance
Re-rate of intercooler and calculation of new corrosion allowance
SVT Engineering Consultants
DV of Ammonia Stripper Vessel
DV of ammonia stripper vessel with replaced bottom section to AS1210
Woodside Energy Ltd
Design of Cable Drums
Design verification for re-rated tube bundle on Air Cooled Heat Exchanger Flash Gas Cooler 5E-4408
PT Heat Exchangers IndonesiaCheck for Custom Reducing Threaded Bush
Update design registration for 3 vessels previously checked
Global Energy Group
Design and Detail of Brine Vessel for BP
Design and detail of replacement brine vessel for BP Refinery to AS1210.Design verification and registration
Apolla MineralsDV of Air Receiver
DV of Air Receiver
ChromaloxDV for Two Electric Heaters
Design Verification for 2 electric heaters
DriairUpdate Design Registration for 3 Vessels
Update design registration for 3 vessels previously checked
KJ BeerPressure Vessel DV
Pressure vessel DV to AS1210. Design registration is excluded
SVT Engineering Consultants
DV of Ammonia Stripper Vessel
DV of ammonia stripper vessel with replaced bottom section to AS1210
Woodside Energy LtdDesign of Cable Drums
Design verification for re-rated tube bundle on air Cooled Heat Exchanger Flash Gas Cooler 5E-4408
PT Heat Exchangers Indonesia
Check for Custom Reducing Threaded Bush
Update design registration for 3 vessels previously checked
Global Energy Group
Design and Detail of Brine Vessel for BP
Design and detail of replacement brine vessel for BP Refinery to AS1210.Design verification and registration of brine vessel
Apolla Minerals
DV of Air Receiver
DV of Air Receiver
ChromaloxDV for Two Electric Heaters
Design verification for 2 electric heaters. Design Verification for 2 tube plates
Driair
Update Design Registration for 3 Vessels
Update design registration for 3 vessels previously checked.
KJ Beer
Pressure Vessel DV
Pressure vessel DV to AS1210.
Woodside Energy Ltd
Reassessment of TEG Contractor Inlet Separator.
Weld procedures
Woodside Energy Ltd
Check of Low Temperature Calculations
Check of Low Temperature Calculation
Clough Engineering
Expander off Gass Silencer
Acid plant
Woodside Energy Ltd
Low Temp Checks for PV
Drum and associated pipe work
Chromalox, France
Natural Gas Heater DV
DV 35.5 W Natural Gas Heater for Chromalox
Woodside Energy Ltd
Rerating of Heat Exchangers
Rerating of existing butted kettles Heat Exchangers.
Cooper Engineer
Design Checks of Tanks
Design checks of tanks
Guntner
DV of 7 Heat Exchangers
Design verification for 7 heat exchangers
Newmont BoddingtonCalculations Review
Review of existing calculations for tank done by KJ Beer
Petroleum & Mining Engineering
Design and Detail of 2 PIGS
Design and Detail of 2 PIGS
Synergy
Modification to Existing Drawings
A vessel previously designed and detailed by CDMS was not built to the drawings. The scope of work is to modify the drawings to reflect the changes
ASG – Ausgroup
Design of dished Heads for Hydro test.
Design of SE heads for hydrotest per DNV standard
Fusion-Weld Engineering P/L
Fusion Welding Design & DV for Vacuum Vessel
Design Verification for Vacuum Vessel
Decmil Australia Pty Ltd
Design Review of Tanks
Design review of tanks
Worley Parsons
DV of Surge Vessel
Design verification for a surge vessel (previously verified) which will be
relocated from Mundaring to Broome. Revised earthquake and wind loads. Design pressure remains the same. No fatigue analysis. Design
registration is excluded
WOMA Australia Pty Ltd
Design of Vacuum Vessel
Design of Vacuum Vessel